By the way, there is no prize for finding the spelling mistake in the excerpt. It is a very lengthy document, I would not be surprised if I have missed something, so if anybody wants to have a look through I would be grateful.
I'm not sure if this is new or not, but the current anticipated transfer date is 4th March 2018. I could be making this up, but I had thought the remapping was going to take place in 2017
"specifies that the Franchisee shall cease to be responsible for the provision of the Passenger Services between Barton-on-Humber and Cleethorpes from the date of commencement of the EMT Franchise (such date currently anticipated to be 01:59 on 4 March 2018)"
The East Midlands franchise was extended for a year, hence the transfer was put back so as to take place at the same time as the new East Midlands franchise.